Projects / Installation & modernisation
Installation & modernisation example
Neville House Gen2 modernisation
A completed Gen2 replacement modernisation at Neville House, London, with equipment supplied by SODIMAS. Work began on 7 April 2026.

Project at a glance.
Location: Neville House, London
Started: 7 April 2026
Programme: seven weeks allowed; completed in approximately five to five-and-a-half weeks.
Equipment supplier: SODIMAS.
Discuss a similar project ↗The project brief.
The Gen2 modernisation covered the machine, drive belts, controls, wiring and door equipment.
Work carried out.
- New machine and drive belts
- New control panel and full rewire
- New door operator
- New landing pushes and indicators
- Firefighting and evacuation system
Programme and completion.
The works were completed in around five to five-and-a-half weeks, within the seven-week programme.
For complete new lift installations, see the SODIMAS ALPHA Motion supply and fit package.
Discuss your modernisation project ↗Project photographs
More from Neville House.
10 photographs across this page. Select a photograph to view it full size.
Planning a lift modernisation?
Explore the supply and fit packages, equipment scope and process.
Explore supply & fit ↗